The RadFxSat (Fox-1B) Mission Readiness Review was held Saturday morning, April 29th, at the Cal Poly campus in front of a board representing Tyvak, Cal Poly, and NASA.
The purpose of the review is to verify that all requirements are met for a safe and successful launch and deployment. Vice President Engineering Jerry Buxton, N0JY, presented 81 PowerPoint slides covering all of the ICD (Interface Control Document) requirements, mission, operations, and deorbit.
At the conclusion of the presentation including questions answers, the panel unanimously approved RadFxSat as ready for flight. The next milestone will be integration into the P-POD with launch scheduled NET (No Earlier Than) September 23, 2017 aboard a Delta II at Vandenberg AFB.