NASA Space Shuttle Discovery's Launch Countdown Begins June 28
NASA will begin the countdown for the launch of Space Shuttle Discovery
at 5 p.m. EDT June 28. The countdown includes nearly 28 hours of
built-in hold time leading to a scheduled launch at about 3:49 p.m. on
July 1. The launch window extends for nearly five minutes. The launch
team at NASA's Kennedy Space Center, Fla., will conduct the countdown
from the newly renovated Firing Room 4 of the Launch Control Center.
This mission is designated STS-121. It is the 115th shuttle flight and
the 18th U.S. flight to the International Space Station. Discovery's
mission is scheduled to last about 12 days and end with 10:45 a.m.
landing at Kennedy on July 13. The crew will test new equipment and
procedures to improve shuttle safety, as well as deliver supplies and
make repairs to the International Space Station.
COUNTDOWN MILESTONES (TIMES SUBJECT TO CHANGE)
Launch-3 Days (Wednesday, June 28): Countdown begins at the T-43 hour
mark (5 p.m.)
Launch-2 Days (Thursday, June 29)
Remove mid-deck and flight-deck platforms (1 a.m.);
Complete preparation to load power reactant storage and distribution
system (4 a.m.)
Activate and test navigational systems (6 a.m.);
Flight deck preliminary inspections complete (9 a.m.)
Enter first built-in hold at T-27 hours for duration of 4 hours (9
a.m.); Clear launch pad of all non-essential personnel; Perform test of
the vehicle's pyrotechnic initiator controllers
Resume countdown (1 p.m.) Begin operations to load cryogenic reactants
into Discovery's fuel cell storage tanks (2:30 p.m.)
Enter 4-hour built-in hold at T-19 hours (9 p.m.); Demate orbiter
mid-body umbilical unit (9:30 p.m.) Resume orbiter and ground support
equipment closeouts
Launch-1 Day (Friday, June 30)
Resume countdown (1 a.m.); Final preparations of shuttle's three main
engines for main propellant tanking and flight (1 a.m.); Begin filling
pad sound suppression system water tank (2 a.m.); Pad sound suppression
system water tank filling complete (5 a.m.); Close out the tail service
masts on the mobile launcher platform
Enter planned hold at T-11 hours for 13 hours, 53 minutes (9 a.m.);
Begin star tracker functional checks (9:50 a.m.); Activate orbiter's
inertial measurement units; Activate the orbiter's communications
systems; Install film in numerous cameras on the launch pad (10:55
a.m.); Flight crew equipment late stow (2:50 p.m.); Move Rotating
Service Structure (RSS) to the park position (6:30 p.m.); Perform ascent
switch list; Fuel cell flow-through purge complete Resume countdown at
T-11 hours (10:53 p.m.)
Launch Day (Saturday, July 1)
Activate the orbiter's fuel cells (12:02 a.m.); Clear the blast danger
area of all non-essential personnel; Switch Discovery's purge air to
gaseous nitrogen (12:53 a.m.)
Enter planned 2-hour built-in hold at the T-6 hour mark (3:53 a.m.);
Launch team verifies no violations of launch commit criteria prior to
cryogenic loading of the external tank; Clear pad of all personnel
Resume countdown (5:53 a.m.); Chill down of propellant transfer lines
(5:53 a.m.); Begin loading the external tank with about 500,000 gallons
of cryogenic propellants (about 6:03 a.m.); Complete filling the
external tank with its flight load of liquid hydrogen and liquid oxygen
propellants (about 8:53 a.m.); Final Inspection Team proceed to launch pad
Enter planned 3-hour built-in hold at T-3 hours (8:53 a.m.); Perform
inertial measurement unit preflight calibration; Align Merritt Island
Launch Area (MILA) tracking antennas; Perform open loop test with
Eastern Range
Resume countdown at T-3 hours (11:53 a.m.); Crew departs Operations and
Checkout Building for the pad (11:58 a.m.); Complete closeout
preparations in the white room
Check cockpit switch configurations; Flight crew begins entry into the
orbiter (about 12:28 p.m.); Astronauts perform air-to-ground voice
checks with Launch and Mission Control. Begin to close Discovery's crew
hatch (about 1:38 p.m.); Begin Eastern Range final network open loop
command checks; Perform hatch seal and cabin leak checks; Complete white
room closeout; Closeout crew moves to fallback area; Primary ascent
guidance data is transferred to the backup flight system
Enter planned 10-minute hold at T-20 minutes (2:33 p.m.); NASA test
director conducts final launch team briefings; Complete inertial
measurement unit preflight alignments
Resume countdown at T-20 minutes (2:43 p.m.); Transition the orbiter's
onboard computers to launch configuration; Start fuel cell thermal
conditioning; Close orbiter cabin vent valves; Transition backup flight
system to launch configuration
Enter estimated 40-minute hold at T-9 minutes (2:54 p.m.); Launch
director, mission management team and NASA test director conduct final
polls for go/no go to launch
Resume countdown at T-9 minutes (about 3:40 p.m.); Start automatic
ground launch sequencer; Retract orbiter crew access arm (T-7:30); Start
mission recorders (T-6:15)
Start Auxiliary Power Units (T-5:00); Arm SRB and ET range safety safe
and arm devices (T-5:00); Start liquid oxygen drainback (T-4:55); Start
orbiter aerosurface profile test (T-3:55); Start main engine gimbal
profile test (T-3:30); Pressurize liquid oxygen tank (T-2:55);
Begin retraction of the gaseous oxygen vent arm (T-2:55); Fuel cells to
internal reactants
(T-2:35); Pressurize liquid hydrogen tank (T-1:57); Deactivate bi-pod
heaters (T-1:52); Deactivate SRB joint heaters (T-0:60 seconds); Orbiter
transfers from ground to internal power (T-0:50 seconds); Ground Launch
Sequencer go for auto sequence start (T-0:31 seconds); SRB gimbal
profile (T-0:21 seconds); Ignition of three space shuttle main engines
(T-6.6 seconds); SRB ignition and liftoff (T-0)
STS-121 CREW & LAUNCH DAY ACTIVITIES
Commander Steve Lindsey; Pilot Mark Kelly; mission specialists Michael
Fossum, Lisa Nowak, Stephanie Wilson, Piers Sellers and Thomas Reiter of
the European Space Agency
# 5:15 a.m. Crew wakes up
# 10:10 a.m. Breakfast
# 10:48 a.m. Weather briefing for STS-121 commander and two crew members
# 11:30 a.m. Astronauts put on flight suits
# 11:58 a.m. Depart for launch pad
# 12:28 p.m. Arrive at white room and begin to enter Discovery
# 1:43 p.m. Close crew hatch
# 3:49 p.m. Launch
For information about the STS-121 crew and its mission to the
International Space Station, visit:
http://www.nasa.gov/shuttle
For NASA TV downlink and scheduling information, visit:
http://www.nasa.gov/ntv
----
Via the sarex mailing list at AMSAT.ORG courtesy of AMSAT-NA.
To unsubscribe, send "unsubscribe sarex" to Majordomo@amsat.org
AMSAT Home