[Date Prev][Date Next][Thread Prev][Thread Next] - [Date Index][Thread Index][Author Index]
SPACE SHUTTLES STATUS S04-33
- Subject: [sarex] SPACE SHUTTLES STATUS S04-33
- From: Arthur Z Rowe <n1orc@xxxxxxxxxxxx>
- Date: Fri, 08 Oct 2004 21:03:16 -0400
- User-Agent: Mozilla Thunderbird 0.7 (Windows/20040616)
Submitted by Arthur - N1ORC- Amsat A/C #31468
Melissa Mathews
Headquarters, Washington Oct. 8, 2004
(Phone: 202/358-1272)
SPACE SHUTTLE PROCESSING REPORT: S04-033
The Space Shuttle fleet is housed and processed at
NASA's Kennedy Space Center (KSC), Fla. The order the Space
Shuttles are listed in this report does not necessarily
reflect the chronological order of future missions.
Discovery (OV-103)
Processing continues in the Orbiter Processing Facility for
Discovery's Return to Flight mission. Throughout the week,
significant progress was made on orbiter system testing.
Technicians continue to bond the new wing leading edge
sensors on the interior of the Reinforced Carbon-Carbon (RCC)
panels. Optics tests continue, with the alignment of the
Manipulator Positioning Mechanisms, in preparation for the
Remote Manipulator System (Space Shuttle arm) installation.
Top NASA and Shuttle management met on Oct. 1. They
determined the March/April target launch window for Return to
Flight is not achievable, due to the impact of recent
hurricanes on agency centers. The council directed the Space
Shuttle Program to assess how it would meet Return to Flight
milestones for the next available launch window, which opens
May 14, 2005. The Shuttle program will present its analysis
at a late October leadership council meeting.
Atlantis (OV-104)
Atlantis is in a four-month power-down period. The critical
path wiring inspections and Return to Flight electrical
modifications continue on schedule. Structural and wire
inspections are ongoing throughout the vehicle.
All right-hand radiators have been installed. Work starts on
the left-hand radiators next week. Right-hand spar fittings
have all been installed, with the full complement of 22 RCC
panels hung on the vehicle. The left-hand wing leading edge
is complete, including the T-seals, which are installed
between each panel.
-more-
-2-
Endeavour (OV-105)
Space Shuttle Endeavour is in its Orbiter Major Modification
period, which began in December. Electrical modifications
continue in the crew module. Three-String Global Positioning
System wire routing in the avionics bay and flight deck
continues.
Right and left-hand wing leading edge corrosion cleanup
continues. Once the RCC panels and associated fittings were
removed, technicians began to bead blast the wing leading
edge of Endeavour to ensure there was no corrosion. The edge
will be painted prior to the reinstallation of RCC panels for
flight. While the panels are removed, they are undergoing
extensive non-destructive testing including flash
thermography and X-rays.
For information about NASA and agency programs on the
Internet, visit:
http://www.nasa.gov
----
Via the sarex mailing list at AMSAT.ORG courtesy of AMSAT-NA.
To unsubscribe, send "unsubscribe sarex" to Majordomo@amsat.org
AMSAT Home