[Date Prev][Date Next][Thread Prev][Thread Next] - [Date Index][Thread Index][Author Index]
SPACE SHUTTLE REPORT #S04-06
- Subject: [sarex] SPACE SHUTTLE REPORT #S04-06
- From: Arthur Z Rowe <n1orc@xxxxxxxxxxxx>
- Date: Fri, 09 Apr 2004 23:02:22 -0400
- User-Agent: Mozilla/5.0 (Windows; U; Windows NT 5.1; en-US; rv:1.5) Gecko/20031013 Thunderbird/0.3
Submitted by Arthur - N1ORC - Amsat #31468
Allard Beutel
Headquarters, Washington April 9, 2004
(Phone: 202/358-4769)
Jessica Rye
Kennedy Space Center, Fla.
(Phone: 321/867-2468)
SPACE SHUTTLE PROCESSING STATUS REPORT: S04-06
The Space Shuttle fleet is housed and processed at NASA's
Kennedy Space Center (KSC), Fla. The order of the Space
Shuttles in this report does not necessarily reflect the
chronological order of future missions.
Discovery (OV-103)
Technicians continue to prepare Discovery for its Return to
Flight mission to the International Space Station. The left-
hand Orbiter Maneuvering System pod was moved from the
Hypergolic Maintenance Facility (HMF) to the Orbiter
Processing Facility (OPF) on Monday for installation on the
vehicle.
Build-up of left-hand Reinforced Carbon-Carbon (RCC) panels
and associated fittings is ongoing with 16 left-hand spar
fittings installed on the vehicle. Thermal Protection System
blanket installation is in work inside of Discovery's nose
cap in the low bay area outside of the Orbiter Processing
Facility. Thermography has been performed on 43 of the 44
panels, with nose cap thermography scheduled for next week.
Atlantis (OV-104)
Processing work continues in the OPF as technicians prepare
Atlantis for its future flight to the International Space
Station. Technicians continue steps toward removal of the
rudder speed brake actuators.
All of Atlantis' 44 RCC panels have been received at KSC, and
all 22 panels have been hung on the left-hand wing. Sixteen
left-hand T-seals, the C-shaped seals that fit between each
panel, have been installed. Build-up of right-hand RCC panels
and associated fittings is ongoing. Nose cap thermography is
complete.
Endeavour (OV-105)
Endeavour is in its Orbiter Major Modification period, which
began in December 2003. The Orbiter Maneuvering System left-
hand pod was transferred from the OPF to the HMF, where it
will undergo routine inspections and maintenance.
Rudder Speed Brake panel removal began yesterday. Actuators
scheduled for removal as early as Monday. RCC thermography
continues with only eight of the 44 panels remaining.
Previous Space Shuttle processing status reports are archived
on the Internet at:
http://www-pao.ksc.nasa.gov/kscpao/status/status.htm
For information about the NASA's Return to Flight efforts on
the Internet, visit:
http://www.nasa.gov/news/highlights/returntoflight.html
For information about NASA and agency programs on the
Internet, visit:
http://www.nasa.gov
-end-
* * *
----
Via the sarex mailing list at AMSAT.ORG courtesy of AMSAT-NA.
To unsubscribe, send "unsubscribe sarex" to Majordomo@amsat.org
AMSAT Home