[Date Prev][Date Next][Thread Prev][Thread Next] - [Date Index][Thread Index][Author Index]

Re: AO-51 commissioning?



On Saturday 17 July 2004 06:22, Greg Wycoff wrote:
> Can someone in close contact with the AO-51 commissioning team advise the
> AMSAT members as to how much has been completed 70% 80% ??? and what that
> means as to how many more days/weeks they are looking at if all goes well
> to complete the commissioning of AO-51.
>
> only those who know, need to answer this question, not interested in
> hearing theory or speculations from those who dont know.
>
> Just wanting to keep our local "AMSAT net" hams up to date, and interested
> in staying involved.
>
>
> AMSAT member 27994
> AMSAT Area Coordinator
> NØZHE
> Greg Wycoff
> Conway Springs, Ks.
> Grid EM17ej
>

Hi Greg,
   just be patient, there is still $9,276 worth of testing to be completed 
once that last bit of money is raised the testing will be completed...LOL

73
Kevin
WA6fwf
#19623
----
Sent via amsat-bb@amsat.org. Opinions expressed are those of the author.
Not an AMSAT member? Join now to support the amateur satellite program!
To unsubscribe, send "unsubscribe amsat-bb" to Majordomo@amsat.org



AMSAT Top AMSAT Home